We are very close to finishing our kitchen. One of the last steps was to close the opening above the top of the wall cabinets.

Since we are our own general contractor, we did not plan for how or when to close that awkward gap above the cabinets. We hired a company to install the cabinets. We hired a plumber to move the piping for the sink and range. We figured we would close that gap above the cabinets eventually. Well, the time has come!
Last month, we hired a contractor to rough-in the framing, plumbing, and electric for a powder room adjacent to the kitchen. He also screwed stud framing above the cabinets for us to finish with drywall.
Jeremy and his dad removed the two wall cabinets and cut and screwed the drywall into the studs. Then we compounded all the seams and installed corner bead on the corners (exactly like the other wall).

The next step is my least favorite. We sanded down the compound so it was smooth. We covered everything in plastic but of course the compound dust still went EVERYWHERE so we had to clean the whole first floor after this step.

Then we painted the new bump-out Simply White by Benjamin Moore. Finally, Jeremy and our friend Logan put the cabinets back after a brief struggle getting them on their tracks!
And just like that, the kitchen is one step closer to being complete! The last three tasks are to tile the backsplash, install the range hood, and paint those last two cursed cabinet doors. And don’t worry, we have the hood duct hiding above the new drywall and ready to attach to our range hood, directly above the stove.